The Building

Building pre-intervention

Building pre-intervention: building before.jpg

Building post-intervention

Building post-intervention: building after_1.jpg
Building post-intervention: building after_2.jpg

Town Hall Burgkunstadt

On the site of the former "Altenburg ob Kunstadt", the Burgkunstädter town hall, one of the most beautiful half-timbered houses in Franconia, has formed the town's skyline for over 300 years. In 1689/90, the master of baroque half-timbered construction, Jörg Hoffmann constructed the impressive decorative half-timbered structure on the early medieval masonry base together with master builder Hans Gebelein . After an inadequate restoration in the 1970s, considerable damage was found on the entire building in 2000. The aim of the overall renovation of the old building was to preserve and emphasise the historical value of this important monument and to equip it for the demands of the present day. All structural measures were implemented in close cooperation with the client and the Bavarian State Office for the Preservation of Historical Monuments.

More Details

The Solution

Solution pre-intervention

Solution pre-intervention: before retrofit_1.JPG.jpg
Solution pre-intervention: before retrofit_2.JPG.jpg

Solution post-intervention

Solution post-intervention: after retrofit_1.JPG.jpg
Solution post-intervention: after retrofit_2.JPG.jpg
What is the Solution?

Replacement of 1970 Box type windows by casement windows with original appearance frame and insulating glazing (double glazing ). A classic drawn glass from the Schott company was used for the exterior panes of the insulating glass windows. This is characterised by its uneven surface, which is created by using the Fourcault method in the manufacturing process.

Why Does it work?

The original appearance of the façade could be retained and from an energy point of view the windows performed well.

PROS
  • a classic drawn glass from the Schott company was used for the exterior panes of the insulating glass windows
  • the original appearance of the façade is retained.
  • the windows were equipped with sun protection.
CONS
  • All new materials.
  • From an energy point of view, insulating glazing was to be installed, although this did not comply with the guidelines of the heritage office
Window Type before retrofit
Box Type Window
Window glass type
Double
Window frame material
Wood
Window position
In the middle
Shading
Interior, new materials, no shading before. Interior roller blind
Health issue
information not available
Installation Method
The existing box-type windows were completely replaced in the renovation process. In addition, they were equipped with sun protection.
Moisture Management and Technical Compatibility
information not available
Airtightness
The existing box-type windows were replaced by new casement windows with better airtightness.

Before retrofit

After retrofit

Before retrofit
Uw-Value
3
After retrofit
Uw-Value
1.3
Before retrofit
Ug-Value
information not available
After retrofit
Ug-Value
information not available
Before retrofit
g-Solar factor
information not available
After retrofit
g-Solar factor
62

Assessment

Window type
Simple window (sash/casement/sliding)
Frame material
Timber
Aesthetic impact
Low Impact (no impact or minor impact from both inside and outside)
Frame improvement
Yes
Glazing improvement
Yes
Additional glazing
Yes
Airtightness improvement
Yes
Window U-value
1 < U <= 2
Shading
Yes - reuse existing appurtenances
Circular approach
Yes
Circular approach (Additional info)
Repairing the frame instead of replacing. Most of the existing windows have been refurbished, with only a few replaced by replicas due to their poor condition. The existing windows were upgraded by replacing the original single glazing with thin, krypton-filled double glazing and adding seals to ensure airtightness.
Investment cost
Medium High

Location

Burgkunstadt, Germany - 306m
Climatic Zone:Cfb